Sanral’s new road tenders contract exposes contractors to higher risks
10 March 2020
Johannesburg – Wednesday, 29 January 2020: Sanral began to roll out tenders worth millions last year for the upgrades to the N2/N3. This is great news for contractors in a sector that is in the doldrums. But, warns construction and technology law specialist MDA Attorneys, amendments to Sanral’s standard contract make it much more difficult for contractors to deal with disruptions related to the construction mafia –where local communities and business forums disrupt sites to demand that they are awarded work under threat of violence, which causes costly delays.
Sanral has added five conditions to the clause on which contractors rely when dealing with strikes and riots, including construction mafia type circumstances. Called force majeure, this clause entitles contractors to claim time extensions, costs and termination of the contract.
“In South Africa, there is a high possibility that local communities and business forums will disrupt the works, which causes prolonged delays and could necessitate ending the project,” says Kelly Meijers, Senior Associate at MDA Attorneys. “Sanral’s previous contract made it difficult for contractors to define these disruptions as force majeure events, but Sanral’s new contract makes it even harder, posing significant risks for contractors.”
Under the new contract, contractors need to have five conditions in place for an event to be considered force majeure:
- The contractor needs to have engaged with those responsible for the disruptions. Specifically, they need to have met with leadership: recorded details, grievances, and any threats made; and asked them to cease the unlawful conduct;
- The contractor must have proof of the riot, commotion, disorder, strike or lockout, and of any unlawful conduct;
- All threats and unlawful conduct must have been reported to the South African Police Service;
- An urgent application must have been launched in court which correctly identifies the parties and defines the unlawful conduct to be interdicted, and
- The contractor must have ensured that the court order is enforced.
Meijers says that contractors who are not aware of the additional requirements are at risk of being unable to obtain time extensions, which may result in delay damages and penalties. “If the conditions do not meet the definition of force majeure, contractors cannot terminate the contract for that reason” she says.
ENDS
High resolution images of Kelly Meijers:
https://drive.google.com/open?id=139iSRu5A2D979wtZbnY9c1_o5gO3Tjr9
For interviews, photographs or further information, please contact Despina Harito at Turquoise PR & Marketing Communications on despina@turquoisepr.co.za 084 453 1755/ 011 568 9036.
About MDA Attorneys
MDA Attorneys is a specialist practice in the field of construction and technology law. It specialises in dispute resolution, commercial support and training. MDA Attorneys’ services include legal advisory solutions to contracting organisations involved in infrastructure, mining, petrochemical, water processing, energy and engineering sectors within southern Africa and internationally.